Criteria
All submitted EC-SDC Grant Program applications shall be reviewed for completeness, technical merit, and adherence to the grant eligibility requirements described in this NOFO. Applications found to be complete and meet ALL eligibility criteria will be prioritized and funded on a first come first served basis. Successful applicants will be notified within approximately 30 days of application submission. Individual grant award amounts were pre-determined based on the total project cost listed on the applicant's PWSLP Funding Nomination Form and availability of EC Principal Forgiveness. Grant funds, if available, may also be awarded to PWSLP Emerging Contaminant projects of small or disadvantaged communities on the funds exhausted list starting March 1st, 2027.
Projects who have been pre-scored to receive grant funds can be found in the PWSLP Intended Use Plan for FY 2027 and, in the table, below:
| Eligible Projects | Loan Numbers | Potential EC-SDC Grant Amount | PWSLP Priority Score |
| Crest Hill | L176383 | $6,650,000 | 695 |
| East Alton | L177281 | $5,837,000 | 455 |
| Tampico | L177429 | $345,000 | 450 |
| Crest Hill | L177610 | $3,050,000 | 405 |
| Keithsburg | L177889 | $2,550,000 | 405 |
| Rockdale | L177317 | $2,386,000 | 385 |
Review and Selection Process
Applicants who submit complete applications and meet all eligibility criteria will be selected for funding. The eligibility criteria are below:
Applicants must have submitted a complete FNF to the Illinois EPA PWSLP, have received approval of a Project Plan meeting the requirements of 35 Ill. Adm. Code 662.320 by March 31st, 2026, and be listed on the Emerging Contaminant - Small or Disadvantaged Community Grant List in the PWSLP Fy2027 Intended Use Plan.
- Applicants must also have a service population below 10,000 or be disadvantaged communities as defined by 35 Ill. Adm. Code 662.210.
- Applicants must be Illinois Community Water Supplies which meet the eligibility requirements of the PWSLP as described in Section 662.130 of the Illinois Procedures for Issuing Loans from the PWSLP.
- Applicant must be registered and pre-qualified through the GATA Grantee Portal, https://grants.illinois.gov/portal/. Registration and pre-qualification are required annually. During GATA pre-qualification, verifications are performed including a check of the federal Debarred and Suspended list and status on the Illinois Stop Payment List. An automated email notification from the GATA Portal to the entity alerts them of ‘qualified’ status or informs how to remediate a negative verification (e.g., inactive UEI, not in good standing with the Secretary of State). A federal Debarred and Suspended status cannot be remediated.
APPLICANTS THAT ARE INELIGIBLE UNDER THIS NOFO:
- Applicants not identified as a disadvantaged community or with a service population above 10,000.
- Applicants who have not submitted an FNF to the PWSLP and have not received planning approval by March 31st, 2026.
- Entities who have been placed in the Illinois Debt Recovery Offset Portal.
- Entities that have NOT satisfied the following GATA pre-qualification requirements:
- Registered with the System for Award Management (SAM) (www.SAM.gov).
- Have a valid Unique Entity Identification (UEI) number.
- Completed an Internal Controls Questionnaire (ICQ) as the fiscal and administrative risk assessment for the current fiscal year – FY 2026 or FY 2027 (when available)
- In good standing with the Illinois Secretary of State.
- Not currently debarred by the State of Illinois and/or federal government.
- Not on the Federal Excluded Parties List.
- Not on the Illinois Stop Payment List.
- Not on the sanctioned party list of the Dept. of Healthcare and Family Services.
- Not on the SAM.gov Exclusion List.
Anticipated Announcement Dates
ACTION BY ILLINOIS EPA | ANTICIPATED DATE |
| Notify applicants that their application was received. | Within approximately 7 days of application submittal to the Illinois EPA. |
| Notify unsuccessful applicants their application was not selected for funding. | Within approximately 30 days of the application submittal deadline. |
| Notify successful applicants that their application was selected for funding. | Within approximately 30 days of the application submittal deadline. |
| Provide a fully executed grant agreement to the grantee | Within 3 months of notification to an applicant that their application was selected for funding. |